Heavy machinery prepared for breakbulk shipping

Breakbulk Trencher Shipment – Dakar to Blyth

Shipment Overview
Origin: Dakar, Senegal
Transhipment Port: Antwerp, Belgium
Final Port: Blyth, United Kingdom
Freight Mode: Breakbulk Sea Freight | Feeder Vessel | OOG Flat Rack
Cargo: Oversized Trencher & Associated Project Equipment
Project Type: Breakbulk Export | OOG Project Cargo | Cost-Optimised Routing

The Challenge
DC Global Freight was appointed to coordinate the return movement of an oversized trencher and associated project cargo from Dakar, Senegal to Blyth in the United Kingdom.

The trencher was unsuitable for conventional containerised transport and required specialist breakbulk handling. Additional operational challenges were present at origin, where sections of port fencing and gates had to be temporarily removed to create sufficient access for the oversized cargo to reach the loading area.

A direct part charter could have provided a more straightforward routing, but transit time was not the principal concern. The priority was to identify the most cost-effective viable shipping solution while maintaining appropriate control over handling and vessel connections.

The shipment therefore required careful planning around vessel availability, port access, transhipment and the differing transport requirements of the cargo pieces.

The Solution
DC Global Freight arranged for the trencher to be loaded in Dakar as breakbulk cargo with top-deck stowage for shipment to Antwerp.

On arrival in Antwerp, the movement was coordinated so that the trencher could be discharged directly to a waiting feeder vessel for onward transport to Blyth.

This routing provided a substantially more cost-effective alternative to arranging a part charter while still maintaining a controlled end-to-end movement.

The remaining project cargo was shipped separately using flat rack equipment, allowing the transport method for each cargo piece to be selected according to its dimensions, weight and handling requirements.

By combining breakbulk and OOG containerised transport within the same overall project, DC Global Freight was able to match the shipping method to the individual cargo characteristics rather than forcing the full shipment into a single transport solution.

The Result
The trencher was successfully routed from Dakar to Blyth via Antwerp using a coordinated breakbulk and feeder vessel solution.

The project achieved the customer’s priority of cost efficiency over transit speed, while also managing the specialist port access, breakbulk loading and transhipment requirements associated with the oversized cargo.

The remaining equipment moved on flat racks, demonstrating how breakbulk and OOG container shipping can be combined within a single project movement to create a practical and commercially efficient logistics solution.

Key Project Facts
• Dakar, Senegal to Blyth, United Kingdom
• Transhipment via Antwerp, Belgium
• Oversized Trencher
• Breakbulk Top-Deck Stowage
• Feeder Vessel Connection
• OOG Flat Rack Cargo
• Port Access Modifications in Dakar
• Direct Vessel-to-Vessel Transfer in Antwerp
• Cost-Optimised Routing
• Alternative to Part Charter
• Mixed Breakbulk & Flat Rack Project Cargo Solution

Heavy machinery shipping and project cargo

Time-Critical Bulldozer Delivery – Felixstowe to UK Trade Show

Shipment Overview

Origin: Shanghai, China
Port of Discharge: Felixstowe, United Kingdom
Freight Mode: OOG Flat Rack Sea Freight | Specialist Road Transport
Cargo: Shantui DH20-M LGP Bulldozer & Toolbox of Parts
Gross Weight: 23,572 kg
Volume: 75.144 CBM
Equipment: 1 × 40ft Flat Rack
Project Type: OOG Import | Flat Rack Unloading | Time-Critical Delivery

The Challenge

DC Global Freight was appointed to coordinate the UK handling and final delivery of a Shantui DH20-M LGP bulldozer arriving at the Port of Felixstowe from Shanghai, China.

The machine had been shipped as out-of-gauge cargo on a 40ft flat rack, with a gross shipment weight of 23,572 kg. Due to the dimensions and configuration of the bulldozer, specialist securing and timber supports had been used for the ocean freight movement.

The critical element of the project was the delivery deadline.

The cargo arrived over the weekend and the importer required the bulldozer to be available by Monday in order to present the machine at a trade show.

This left a very restricted operational window to coordinate the release of the cargo, arrange specialist unloading from the flat rack and complete the onward delivery within the required deadline.

The Solution

DC Global Freight coordinated the operation around the weekend arrival and the fixed Monday delivery requirement.

Once the cargo became available, arrangements were made for the bulldozer to be safely removed from the 40ft flat rack, including the release of the securing arrangements used to protect and restrain the machine during the ocean voyage.

The operation required close coordination between the depot, specialist handling personnel and the onward transport provider to minimise delays between cargo availability, unloading and collection.

Following removal from the flat rack, the bulldozer was prepared for onward transport and dispatched for final delivery.

By coordinating each stage against the fixed deadline, DC Global Freight ensured the machine was delivered on Monday in time for the importer to present it at the trade show.

The Result

Despite the cargo arriving over a weekend and the extremely limited delivery window, the complete UK operation was successfully coordinated within the required timeframe.

The bulldozer was removed from the flat rack, transferred to specialist road transport and delivered by the Monday deadline.

The project demonstrates the importance of responsive freight management when project cargo movements are governed not only by vessel schedules and cargo availability, but by a non-negotiable commercial deadline at destination.

Key Project Facts

• Shantui DH20-M LGP Bulldozer
• Shanghai, China to Felixstowe, UK
• 1 × 40ft Flat Rack
• Gross Weight: 23,572 kg
• Volume: 75.144 CBM
• Out-of-Gauge Project Cargo
• Weekend Cargo Arrival
• Specialist Flat Rack Unloading
• Time-Critical UK Road Transport
• Fixed Monday Delivery Deadline
• Delivered in Time for Trade Show Presentation

OOG ROV systems secured for export from Middlesbrough to Istanbul

OOG ROV Systems Export – Middlesbrough to Istanbul

Shipment Overview

Origin: Middlesbrough, United Kingdom
Port of Loading: Felixstowe, United Kingdom
Port of Discharge: Istanbul, Turkey
Freight Mode: OOG Flat Rack & Containerised Sea Freight
Equipment: 8 × 40ft Flat Racks | 2 × 20ft Flat Racks | 1 × 20ft GP
Cargo: ROV Systems & Associated Subsea Equipment
Project Type: OOG Export | ROV Equipment | Flat Rack Shipping | Project Cargo Logistics

The Challenge

DC Global Freight was appointed to coordinate the export of a substantial consignment of ROV systems and associated subsea equipment from Middlesbrough, UK to Istanbul, Turkey.

The project involved multiple pieces of specialist and oversized equipment requiring eight 40ft flat racks, two 20ft flat racks and one 20ft general-purpose container.

Due to the dimensions and configuration of the equipment, the flat racks needed to be loaded and professionally secured at origin before being transported to Felixstowe for export.

Careful coordination was required between the site, specialist loading and lashing teams, transport operators and ocean freight arrangements to ensure the equipment was safely prepared and delivered to port within the required shipping schedule.

The Solution

DC Global Freight coordinated the complete export logistics operation from collection in Middlesbrough through to shipment from Felixstowe.

The ROV systems and associated subsea equipment were carefully allocated across the flat rack and container equipment according to their dimensions, configuration and handling requirements.

Specialist loading and securing arrangements were coordinated to ensure the cargo was correctly positioned and professionally lashed for international sea transport. The oversized flat rack units were then transported by suitable specialist vehicles from Middlesbrough to Felixstowe.

DC Global Freight also coordinated the ocean freight arrangements for the complete consignment, ensuring the multiple units were managed as one project shipment through to Istanbul.

The Result

The complete ROV systems shipment was successfully prepared, secured and transported from Middlesbrough to Felixstowe for onward sea freight to Istanbul.

By coordinating the specialist loading, lashing, road transport and ocean freight requirements as a single project movement, DC Global Freight provided a controlled logistics solution for a complex multi-unit subsea equipment export.

Key Project Facts

• ROV Systems & Associated Subsea Equipment
• Middlesbrough, UK to Istanbul, Turkey
• Export via Felixstowe
• 8 × 40ft Flat Racks
• 2 × 20ft Flat Racks
• 1 × 20ft General-Purpose Container
• Specialist Loading & Lashing
• OOG & Project Cargo Transport
• Multi-Unit Ocean Freight Coordination

OOG concrete bridge section secured to 40ft flat rack for shipment to Dakar Senegal

OOG Concrete Bridge Shipment – UK to Senegal

Shipment Overview

Collection:
Great Yarmouth, United Kingdom

Port of Loading:
London Gateway

Port of Discharge:
Dakar, Senegal

Freight Mode:
OOG Sea Freight | 40ft Flat Rack

Cargo:
Concrete Bridge Sections & Concrete Mattresses

Equipment:
6 × 40ft Flat Racks – Concrete Bridge Sections
2 × 40ft Flat Racks – Concrete Mattresses

Concrete Bridge Unit Dimensions:
7.00m × 3.80m × 2.01m

Concrete Bridge Unit Weight:
36,160 kg

The Challenge

DC Global Freight was appointed to coordinate the movement of oversized and heavy concrete bridge sections and concrete mattresses from Great Yarmouth to Dakar, Senegal.

The concrete bridge sections measured 7.00m × 3.80m × 2.01m and weighed 36,160 kg per unit, requiring specialist out-of-gauge transport planning and 40ft flat rack equipment.

The project required coordination of the cargo movement from Great Yarmouth to London Gateway, preparation for export shipment and onward ocean freight to Dakar.

The Solution

DC Global Freight coordinated the shipment using eight 40ft flat racks, comprising six flat racks carrying concrete bridge sections and two flat racks carrying concrete mattresses.

The cargo was transported from Great Yarmouth to London Gateway for export, with the oversized bridge sections secured to flat rack equipment for the ocean movement to Dakar.

The operation required careful coordination between the transport, port and shipping elements of the project to manage the heavy and out-of-gauge cargo through each stage of the shipment.

The Outcome

The project provided a coordinated logistics solution for the movement of specialist concrete infrastructure cargo from the UK to Senegal, combining heavy transport, OOG flat rack equipment, port handling and international sea freight.

Key Project Facts

• 8 × 40ft Flat Racks
• 6 × 40FR – Concrete Bridge Sections
• 2 × 40FR – Concrete Mattresses
• Bridge Unit Weight: 36,160 kg
• Bridge Dimensions: 7.00m × 3.80m × 2.01m
• Great Yarmouth → London Gateway → Dakar
• Heavy & Out-of-Gauge Project Cargo
• UK to Senegal Project Logistics ~   £

HERO_IMG_1669

Deep Panuke Offshore Decommissioning Project – Canada to UK

Shipment Overview

Project:
Deep Panuke Offshore Decommissioning Project

Origin:
Sheet Harbour, Nova Scotia, Canada

Port of Loading:
Halifax, Canada

Port of Discharge:
Liverpool, United Kingdom

Final Deliveries:
Aberdeen & Great Yarmouth, United Kingdom

Freight Modes:
Project Cargo | Ocean Freight | Road Transport

Cargo:
Specialist Offshore Decommissioning Equipment

Project Type:
Offshore Equipment Demobilisation & UK Reimport

The Challenge

DC Global Freight coordinated the return of a substantial package of specialist offshore equipment from Nova Scotia, Canada, following its deployment in connection with the Deep Panuke offshore decommissioning project.

The operation involved numerous pieces of specialist offshore equipment of varying dimensions and weights, including high-pressure water pumps, compressors, cutting equipment, hydraulic power units, an overboard frame, umbilical equipment, offshore containers, rigging and associated tooling.

The cargo also included abnormal-length and heavy units together with equipment requiring dangerous goods handling, creating a complex multi-modal logistics operation.

Following completion of the offshore work, the equipment needed to be consolidated and transported from Sheet Harbour, Nova Scotia, before shipment back to the United Kingdom and onward delivery to multiple UK destinations.

The Solution

DC Global Freight developed and coordinated the logistics programme for the equipment demobilisation and return to the UK.

The operation required coordination of the cargo from Sheet Harbour, preparation and consolidation of the various equipment packages, Canadian road transport, ocean freight and subsequent UK distribution.

Cargo was shipped from Halifax to Liverpool, where the operation required coordinated vessel discharge and handling of the specialist equipment before onward road transport.

Following arrival in the UK, DC Global Freight coordinated customs reimport procedures and the onward movement of the equipment to its respective UK destinations, including Aberdeen and Great Yarmouth.

Careful coordination between overseas partners, vessel operators, port handling teams, customs representatives and specialist road transport providers was required throughout the operation.

Execution

  • Offshore equipment demobilisation planning
  • Cargo consolidation in Nova Scotia
  • Specialist Canadian road transport
  • Heavy and abnormal cargo coordination
  • Dangerous goods management
  • Export and shipping documentation
  • Ocean freight from Halifax to Liverpool
  • Vessel discharge and UK port handling
  • UK customs reimport coordination
  • Specialist onward road transport
  • Multiple final delivery locations
  • Dedicated project logistics management

The diverse cargo profile required each equipment package to be assessed individually so that suitable transport, handling and shipping arrangements could be coordinated throughout the supply chain.

The Outcome

DC Global Freight successfully coordinated the return of the specialist offshore equipment from Nova Scotia to the United Kingdom following its deployment in connection with the Deep Panuke offshore decommissioning project.

The operation brought together international road transport, ocean freight, port operations, customs reimport procedures and final UK distribution within a single coordinated project logistics solution.

Following discharge in Liverpool, equipment was successfully routed onwards to its respective UK destinations, including Aberdeen and Great Yarmouth.

The project demonstrates DC Global Freight’s capability to manage complex offshore energy logistics, project cargo demobilisation and the international movement of specialist equipment involving multiple transport modes, cargo types and delivery locations.

Key Project Facts

  • Deep Panuke Offshore Decommissioning Project
  • Demobilisation from Nova Scotia, Canada
  • Specialist offshore equipment
  • Heavy & abnormal-load cargo
  • Multiple equipment packages
  • Dangerous goods handling
  • Halifax to Liverpool ocean freight
  • Coordinated vessel discharge
  • UK customs reimport
  • Onward deliveries to Aberdeen & Great Yarmouth
  • Multi-modal project logistics coordination
01_HERO_Night_Convoy

147.6Te Yankee Dryer Heavy Lift Delivery – Shotton Mill

Shipment Overview

Delivery Location: Shotton Mill, United Kingdom
Freight Modes: Heavy Lift Road Transport | Project Cargo
Cargo: Valmet Advantage Yankee Dryer
Dimensions: 8.96m × 5.62m × 5.72m
Gross Weight: 147.6Te
Specialist Equipment: 16 Axle Girder Frame Trailer | Hydraulic Jacking & Skidding Systems
Project Type: Heavy Lift Industrial Cargo Delivery and Site Positioning

The Challenge

DC Global Freight coordinated the specialist transport, unloading, and final positioning of a 147.6Te Yankee Dryer destined for Shotton Mill as part of a major industrial project.

Due to the cargo dimensions of 8.96m x 5.62m x 5.72m and the overall cargo weight, the operation required extensive route planning, engineering analysis, specialist trailer configuration, and controlled movement procedures throughout the transport operation.

The delivery involved complex heavy haulage movements across UK roads, escorted transport operations, night-time movements, and detailed coordination between lifting engineers, transport crews, and site teams.

The project also required precise hydraulic jacking and lifting procedures to safely unload and position the cargo within the project site.

The Solution

DC Global Freight coordinated the full heavy lift operation using a specialist 16 axle girder frame trailer combined with engineered lifting and positioning procedures.

The transport operation was carefully planned to manage axle loadings, route restrictions, site access limitations, and operational safety requirements.

Following delivery to site, specialist hydraulic jacking systems and lifting beams were utilised to safely unload and position the Yankee Dryer under controlled engineering supervision.

Close coordination between transport operators, lifting specialists, site personnel, and project management teams ensured all operational stages were completed safely and efficiently.

Execution

The operation involved:

• Heavy lift route planning and transport coordination
• Escort vehicle and controlled convoy management
• Specialist 16 axle girder frame trailer configuration
• Night-time transport operations
• Hydraulic lifting and lowering procedures
• Specialist jacking and skidding systems
• Engineering supervision and safety management
• Cargo unloading and final positioning
• Site coordination and operational planning
• Dedicated heavy lift project management

Detailed engineering planning and controlled execution ensured the cargo could be transported, unloaded, and positioned safely at the final destination.

 

The Outcome

DC Global Freight successfully coordinated the safe transport, unloading, and final positioning of the 147.6Te Valmet Advantage Yankee Dryer at Shotton Mill.

The project demonstrated DC Global Freight’s capability in managing complex heavy lift and industrial logistics operations involving oversized cargo, specialist transport equipment, hydraulic lifting systems, and engineered delivery solutions.

The operation was completed safely, efficiently, and in line with project delivery requirements.

 

 

Key Project Facts

• Cargo: Valmet Advantage Yankee Dryer
• Gross Weight: 147.6Te
• Dimensions: 8.96m × 5.62m × 5.72m
• Transport: 16 Axle Girder Frame Trailer
• Specialist Hydraulic Jacking & Skidding Systems
• Escorted & Controlled Road Movements
• Heavy Lift Engineering Coordination
• Final Site Delivery & Positioning – Shotton Mill

IMG_3231

Covid Charter Vessel Operations – China to UK

Shipment Overview

Ports of Loading:
Ningbo & Shanghai

Ports of Discharge:
Liverpool & Teesport

Freight Modes:
Sea Freight | Road Freight | Rail Freight

Vessels:
– Tasmanic Winter
– Saga Faith
– Saga Flora
– BBC Ukraine
– UniSpace

Project Type:
Full charter vessel operations during the Covid shipping disruption period.

The Challenge

During the Covid pandemic, global shipping markets faced severe disruption including container shortages, port congestion, reduced vessel availability, and major delays across international supply chains.

Maintaining reliable cargo movement from China to the UK became increasingly difficult for importers relying on consistent freight capacity and predictable transit times.

The project required DC Global Freight to secure dedicated vessel space and coordinate large-scale cargo movement under extremely challenging global shipping conditions.

The Solution

DC Global Freight coordinated the direct charter of five container vessels operating from Ningbo and Shanghai to Liverpool and Teesport.

By arranging full charter vessel operations, the shipments avoided additional port calls and significantly reduced transit complexity during a period of major global disruption.

The project also required coordinated UK transport planning using both road and rail freight solutions to ensure cargo distribution continued efficiently after discharge.

Execution

The operation involved:
– Direct vessel charter coordination
– International freight planning
– Multi-modal transport management
– UK road freight coordination
– Rail freight support
– Port discharge planning
– Ongoing shipment communication and visibility

Dedicated charter arrangements enabled faster and more reliable cargo movement compared to heavily congested standard shipping services operating during the Covid period.

The Outcome

DC Global Freight successfully managed full charter vessel operations carrying up to 5000 TEUs during one of the most challenging periods in modern global shipping.

The project provided:
– Faster transit times
– Reduced supply chain disruption
– Reliable cargo movement
– Improved shipment control
– Efficient UK distribution support

By securing dedicated vessel capacity and coordinating multi-modal delivery solutions, DC Global Freight helped maintain critical supply chain continuity for UK import operations during the Covid shipping crisis.

Key Project Facts

– Full charter operations of 5 vessels
– Up to 5000 TEUs carried
– Direct China to UK routing
– No additional port calls
– Multi-modal UK distribution
– Coordinated road and rail freight delivery